Monday 6 August 2012

White Pit 18/4/12

Estelle Sandford, Mark Denning, Stu Gardiner, later joined by Mike Moxon & Henry Dawson
3hrs
Took down drill, etc. and generator to bolt some of the bars in place with anchor bolts, also removed a bit more rock to make sure we were back at secure rock. All three of the short lengths bolted into place, now need to bring down some cut down railway sleepers and cement lots or rock in. Mike & Henry brought some cement and Henry started a project to build a shed construction on the surface to house the air pump and generator while we are digging. They made a start on that.